Calendar Exceptions

This forum includes discussion about project risk analysis and risk management theory: Monte Carlo simulations, Event Chain Methodology, schedule and cost risk analysis. Please submit questions and case studies about your experience with our project risk analysis software.

Moderator: Intaver Support

Post Reply
NTT
Posts: 24
Joined: Sun May 27, 2007 4:51 pm
Location: Boston, MA

Calendar Exceptions

Post by NTT » Mon Apr 10, 2017 6:48 pm

I have calendar exception in MS Project (holidays). Will they be imported to RiskyProject if I use RiskyProject Addin or XML export?
risk manager

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Calendar Exceptions

Post by Intaver Support » Mon Apr 10, 2017 6:50 pm

Quick answer is yes. Call calendars in the MS Project schedule including resources and task calendars are included when you import using either the Addin or xml.
You can check to ensure you calendars have imported correctly in the Working Time dialog box. Select the calendar from the drop-down list and exceptions will be marked accordingly.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Post Reply