Assigning risks to multiple resources

Post by TonyR » Sat May 20, 2017 6:25 am

I have a risk that could impact a number of resources. Is there any way to do this quickly?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Assigning risks to multiple resources

Post by Intaver Support » Sat May 20, 2017 6:37 am

As with tasks, you can use the Drag N’ Drop view to assign a risk to multiple resources at one time.
To do this, go to Risks > Drag N’ Drop view. On the bottom of the right hand pane, click Resources. This will list all the project resources. Highlight the resources to which you want to assign the risk. Click on the risk and drag it over the highlighted resources.

Image

The Assign risk to task or resource dialog box opens. Add the chance the risk will occur and the outcome type and outcome. Click Ok to finish.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com