Fixed delay from 2 to 10 days

Posted: Sun Jan 07, 2018 12:05 pm
by Hato
Is any way to define risk outcome within certain margins? For example, I have a task than can be delayed in case of certain risk 2 – 10 days. I don’t know exactly on how much

Re: Fixed delay from 2 to 10 days

Posted: Sun Jan 07, 2018 12:29 pm
by Intaver Support
In order to define range of results for risk outcomes, you need to go to Options (Portfolio Options) in RiskyProject Enterprise and Enable statistical distribution of risk outcomes:

Image

This information will be saved in risk register on in database (for RiskyProject Enterprise).

Then you can define distribution type as well as low, base, and high outcomes for risk assignment in risk tab of Task Information Dialog.
Image

If you double click on risk assignment ID within Risk tab of Task Information Dialog you will be able to edit parameters for the statistical distribution of risk outcome.
Image