Page 1 of 1

Split Tasks

Posted: Tue May 01, 2018 11:05 am
by PMBOK
Does RiskyProject supports split tasks as Microsoft Project?

Re: Split Tasks

Posted: Tue May 01, 2018 11:08 am
by Intaver Support
When you import a split task into RiskyProject from MS Project, the task itself will not be split, but the Start and Finish times will. This means that during the Monte Carlo simulation the finish and start times will be used to model how uncertainties will affect the project; however, if you are using resource loaded schedules, you need to account for the additional work that RiskyProject will add to the “split tasks” because of how they are handled.

Image