Page 1 of 1

Event chain in RiskyProject

Posted: Sat Mar 10, 2007 6:39 pm
by Strategy Table
How can I model event chain in RiskyProject?

Posted: Sun Mar 11, 2007 10:03 am
by Intaver Support
Currently you can define event chain using risk correlation. To do it enter necessary local or global risks and go to risk correlation tab of local risk dialog box. Correlated risks occur together rather than independently.

In future versions of RiskyProject we will offer special risks: start other activity, change probability of risk in another activity, and others. This risk event will also help you to generate event chains.

Re: Event chain in RiskyProject

Posted: Thu Jan 03, 2013 8:29 am
by Tomico
I want to define correlations between risks. How to do it?

Re: Event chain in RiskyProject

Posted: Thu Jan 03, 2013 8:34 am
by Intaver Support
Risk Correlations can be entered in Risk Information Dialog for local and global risk assignment. You may access this dialog by double clicking on Risk ID within a list of local risks or in global risk view. You need to select the risk, current risk will be corrected with.

1. Go to Global or Local Risk Assignment view
2. Click on ID of the particular risk assignment. Risk assignment dialog opens
3. Go to correlation tab.
4. Select risk(s) correlated with this particular risk