Cost and time uncertainties

Posted: Tue Oct 23, 2007 5:45 pm
by PetroleumCons
Is it possible to define uncertainties in cost and time at the same time? We have a number of risks, which affects project schedule and project cost.

Posted: Tue Oct 23, 2007 5:53 pm
by Intaver Support
Yes, you may define risk 'Increase duration' or 'restart task' as well as risk 'Increase cost'. We don't have specific risk 'increase cost and duration'. But you may create two separate risks and use risk correlation mechanism to ensure that they occur together. Please remember, this 'increase cost' risk is related to fixed cost only.