Can Deadline be used to automatically adjust schedules

This forum focus on project portfolio risk management theory and RiskyProject Enterprise software. Submit any questions about enterprise risk management, and qualitative / quantitative risk analysis for multiple projects. This forum also includes discussions about project risk analysis on the enterprise level.

Moderator: Intaver Support

Post Reply
NTT
Posts: 25
Joined: Sun May 27, 2007 4:51 pm
Location: Boston, MA

Can Deadline be used to automatically adjust schedules

Post by NTT »

I am trying to set a dead as the absolute latest a project can finish, therefore any risks or delays in tasks should result in them being set to start earlier with the results Gantt. Do you know if this is possible? I am trying to have the risk show tasks having to start earlier to meet the fixed deadline rather than extend out beyond it.
risk manager
Intaver Support
Posts: 999
Joined: Wed Nov 09, 2005 9:55 am

Re: Can Deadline be used to automatically adjust schedules

Post by Intaver Support »

With deadlines the results will only show that it fails to meet the deadline. It does not compress the schedule as you would like. Typically, schedule compression or acceleration requires a complete rework of the schedule including adding additional resources, more parallel activities. etc as required.
The only thing we can offer is generating a new schedule from the results using the export to xml feature. In this case you would have to find p level that meets the deadline. However, this schedule could be very optimistic depending upon the P level selected.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Post Reply