This forum focus on project portfolio risk management theory and RiskyProject Enterprise software. Submit any questions about enterprise risk management, and qualitative / quantitative risk analysis for multiple projects. This forum also includes discussions about project risk analysis on the enterprise level.

Moderator: Intaver Support

Post Reply
Daniel001
Posts: 12
Joined: Tue Apr 27, 2010 7:00 am
Location: Canada
Contact:

Master Schedules

Post by Daniel001 » Fri Oct 21, 2016 3:42 pm

How does RiskyProject manage MS Project Master schedules?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Master Schedules

Post by Intaver Support » Fri Oct 21, 2016 4:01 pm

Essentially RiskyProject merges a master schedule with n subprojects into 1 large schedule. Cross project links are converted into standard links such as in a schedule in MS Project is converted to RiskyProject schedule. You will not notice this if you run the analysis using the RiskyProject MSP Addin; however, if you open the Master Project in RiskyProject you will see that cross project links are shown as a standard link in the Predecessors tab of the Task Information view.

In addition, if you compare the task numbering, RiskyProject renumbers all tasks in the Master Schedule; whereas in MS Project each subproject has its own task numbering. Because MS Master Projects do not have unique task numbers (there can be n Task 1s etc.) this RiskyProject relies on unique WBS IDs to properly convert the subprojects to a single project file.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject