This forum focus on project portfolio risk management theory and RiskyProject Enterprise software. Submit any questions about enterprise risk management, and qualitative / quantitative risk analysis for multiple projects. This forum also includes discussions about project risk analysis on the enterprise level.

Moderator: Intaver Support

Post Reply
Stu1
Posts: 10
Joined: Thu May 04, 2006 3:50 pm
Location: LA, CA

Cost Type Resources

Post by Stu1 » Tue Apr 25, 2017 5:13 pm

Do you have cost resources in RiskyProject and RiskyProject Enterprise as in MS Project?

bbadmin
Site Admin
Posts: 18
Joined: Tue Nov 08, 2005 8:34 pm

Re: Cost Type Resources

Post by bbadmin » Tue Apr 25, 2017 5:15 pm

Yes, Cost type resources can be read in from MS Project as well, can be created in RiskyProject.
To assign a cost type resource to a task. Open the Resources view in RiskProject. Type in the source name and select Cost as the type.

Image

Open the Project View and to assign the resource with a cost double-click on a task and click the Resources tab. Add the resource and then enter in the cost of the resource. In the example, below, Resource 2 will have a cost of $1000.

Image