Cost Type Resources

Posted: Tue Apr 25, 2017 5:13 pm
by Stu1
Do you have cost resources in RiskyProject and RiskyProject Enterprise as in MS Project?

Re: Cost Type Resources

Posted: Tue Apr 25, 2017 5:15 pm
by bbadmin
Yes, Cost type resources can be read in from MS Project as well, can be created in RiskyProject.
To assign a cost type resource to a task. Open the Resources view in RiskProject. Type in the source name and select Cost as the type.

Image

Open the Project View and to assign the resource with a cost double-click on a task and click the Resources tab. Add the resource and then enter in the cost of the resource. In the example, below, Resource 2 will have a cost of $1000.

Image