Assigning distributions to multiple tasks

Posted: Tue May 02, 2017 9:06 pm
by Ken
Can I assign beta distribution to multiple tasks at the same time?

Re: Assigning distributions to multiple tasks

Posted: Tue May 02, 2017 9:13 pm
by Intaver Support
Yes, you can do this by selecting the tasks to which you want to assign the distribution and right-clicking on the Task ID column. Click Set Low/high Duration and a dialog box opens that not only allows you to assign a distribution type, but also add low and high estimates for duration.

Image

Re: Assigning distributions to multiple tasks

Posted: Tue May 02, 2017 9:16 pm
by Ken
What if tasks belong to different projects? Can I assign distribution to all tasks in selected projects at the same time?

Re: Assigning distributions to multiple tasks

Posted: Tue May 02, 2017 9:17 pm
by Intaver Support
No. When you assign distributions you can do it for current (opened) project.