Modifying Risk History

Posted: Wed Jul 26, 2017 11:47 am
by G&G
Can I change dates in risk history?

Re: Modifying Risk History

Posted: Wed Jul 26, 2017 11:49 am
by Intaver Support
If you have administrator permissions or are using the standalone versions you can always modify the dates in the Risk History dialog. Simply open the Risk Register and double-click on a risk to open the Risk Information dialog box. Click the History tab. Locate the entry and click in the date box to open the calendar. Change the date as required and click OK to save your changes. If the date field is greyed out, you do not have permission to change the entry and should contact your administrator.