Links to external activites

General discussion and questions about project risk management and risk analysis software RiskyProject. Includes discussion on how to perform efficient project risk analysis using our software.

Moderator: Intaver Support

Post Reply
Hato
Posts: 20
Joined: Tue Jun 01, 2010 5:34 am
Location: US
Contact:

Links to external activites

Post by Hato » Wed Dec 08, 2010 9:21 am

Normally our projects are going to have links to an external master project. Currently, when performing risk analysis, we remove this links manually and insert a nomincal task that has similar start and finish dates.
When I import our projects into RiskyProject the links do not even appear. Is there a workaround this?
Project manager

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

External links

Post by Intaver Support » Wed Dec 08, 2010 9:26 am

In RiskyProject 3.2 there external links are ignored, this is due to the limitations of the MS project xml or the mpx formats that we use to read in project schedules.

We are currently developing a solution for this that will be incorporated into version 4. This will read the external link data, but will not read in the lnk data as a whole, rather the external dates will be handled using constraints.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Post Reply