Mitigation and Response plan view

General discussion and questions about project risk management and risk analysis software RiskyProject. Includes discussion on how to perform efficient project risk analysis using our software.

Moderator: Intaver Support

Post Reply
Ken
Posts: 65
Joined: Wed Nov 09, 2005 9:47 am
Location: California

Mitigation and Response plan view

Post by Ken » Thu Mar 24, 2016 3:43 pm

Can I create a hierarchy of mitigation and response plan and Mitigation and Response view?
Ken the PM

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Mitigation and Response plan view

Post by Intaver Support » Thu Mar 24, 2016 3:54 pm

Yes, the Mitigation and Response Plans view supports hierarchies similar to how you would set up Summary and sub tasks in a Gantt Chart.
To create a subplans:

1. Create a plan. You can do this by simply typing a name into the name field, This will be the Plan
2. Under your plan, create another plan. You should now have two plans.
3. Select the second plan.
4. Click the outdent button on Structure > Outdent.

It is possible to create multiple levels.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com