Risk score calculation algorithm

This forum includes discussion about project risk analysis and risk management theory: Monte Carlo simulations, Event Chain Methodology, schedule and cost risk analysis. Please submit questions and case studies about your experience with our project risk analysis software.

Moderator: Intaver Support

Post Reply
David
Posts: 19
Joined: Tue Jan 15, 2008 4:33 am
Location: UK

Risk score calculation algorithm

Post by David » Tue Aug 16, 2016 3:08 pm

What is the risk score calculation algorithm in RiskyProject if I have risk which belong to different categories?
PMP, M.Sc.

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Risk score calculation algorithm

Post by Intaver Support » Tue Aug 16, 2016 3:39 pm

Risk score is calculated as probability multiplied on impact. In example below risk 'Delay in Financing' has a probability 65% impact 52%. The score equals 33.8%. However if risk affects multiple categories the calculation is a little but more complex. Risk impact for each risk category is multiplied on weight or 'overall importance' of each category. Weight is calculated using matrix, which can be found at Risk -> Risk Categories -> Weights. Then impacts for all categories are summed together. Finally they are normalized such way maximum impact cannot be greater than 1. Then scores for each risks are calculated.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com