Default Task Types

Post by Tomico » Wed Feb 06, 2019 3:01 pm

Can you set a default task type?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Default Task Types

Post by Intaver Support » Wed Feb 06, 2019 3:06 pm

Yes. In the Project Options > Duration tab you an set the default Task Type. If you do not manually change this default setting, the Task Type is set to Fixed Units.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Tomico
Posts: 63
Joined: Thu May 18, 2006 5:02 pm
Location: Naples, FL

Re: Default Task Types

Post by Tomico » Tue Feb 19, 2019 10:22 am

By default, RiskyProject has Fixed Units set as the Task Type. Is there a reason for this?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Default Task Types

Post by Intaver Support » Tue Feb 19, 2019 10:23 am

Fixed Units is probably the best task type for schedule risk analysis because of the manner in how task types are used to recalculate Work, Units, or Duration. In Monte Carlo simulations, we are measuring how changes to task durations can not only affect project duration and finish time, but also how the amount of effort (hours of work) and therefore resource costs these variances could cause. Therefore using Fixed Work or Fixed Duration would not allow you to simulate the results that you require. Fixed Work would not allow you to measure the variance in time dependent costs and Fixed Duration would not allow you to measure the variance in task and project durations and finish times.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Default Task Types

Post by Intaver Support » Mon Apr 01, 2019 4:03 pm

Actual definition of task types can be found here: http://www.intaver.com/IntaverFrm/viewtopic.php?t=1272