Applying Risks to Consolidated Schedules

This forum includes discussion about project risk analysis and risk management theory: Monte Carlo simulations, Event Chain Methodology, schedule and cost risk analysis. Please submit questions and case studies about your experience with our project risk analysis software.

Moderator: Intaver Support

Post Reply
Tomico
Posts: 63
Joined: Thu May 18, 2006 5:02 pm
Location: Naples, FL

Applying Risks to Consolidated Schedules

Post by Tomico »

Can risks be applied before and/or after a schedule has been consolidated?
Intaver Support
Posts: 1008
Joined: Wed Nov 09, 2005 9:55 am

Re: Applying Risks to Consolidated Schedules

Post by Intaver Support »

Risks should be applied after consolidation has been performed. If a risk is applied to a single activity prior to consolidation, it will be assigned with the same probability and impacts to a consolidated task and which may not be optimal.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Post Reply