Crucial Tasks
What is the diffence between critical tasks and crucial tasks?
-
- Posts: 1018
- Joined: Wed Nov 09, 2005 9:55 am
Critical tasks are the tasks on the critical path. Crucial tasks are calculated as a result of sensitivity analysis.
Crucial Tasks are those tasks, according to the sensitivity analysis, whose duration has the most affect on a project’s duration and finish time are crucial tasks. Uncertainties related to critical tasks should be assessed and the risks associated with these tasks should be mitigated. Crucial tasks are displayed on the Gantt chart using distinct colors.
Crucial Tasks are those tasks, according to the sensitivity analysis, whose duration has the most affect on a project’s duration and finish time are crucial tasks. Uncertainties related to critical tasks should be assessed and the risks associated with these tasks should be mitigated. Crucial tasks are displayed on the Gantt chart using distinct colors.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
-
- Posts: 1018
- Joined: Wed Nov 09, 2005 9:55 am
RiskyProject calculates only crucial tasks. Critical tasks and crucial tasks can be different.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com