I downloaded RP few days ago. I like simplicity and emphasize on event rather than on statistical distributions.
Could you tell me how do you calculate success rate?
Regards,
Sandra,
Nissan Canada
Success Rate
Moderator: Intaver Support
-
- Posts: 1018
- Joined: Wed Nov 09, 2005 9:55 am
Success rate is reduced when task is canceled. A task can be canceled in one of three cases:
1. If the outcome Cancel task or Cancel task + all successors occurs, this cancels the tasks plus all successors which have occurred;
2. If a task reaches a deadline, and action associated with deadline is set to cancel task; and
3 If a project has reached a deadline and task finish time is beyond the deadline.
1. If the outcome Cancel task or Cancel task + all successors occurs, this cancels the tasks plus all successors which have occurred;
2. If a task reaches a deadline, and action associated with deadline is set to cancel task; and
3 If a project has reached a deadline and task finish time is beyond the deadline.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com