Primavera integration task links
Unlike MS Project, Primavera supports tasks that have both FF and SS link between them. Is this supported in RiskyProject?
risk manager
-
- Posts: 1018
- Joined: Wed Nov 09, 2005 9:55 am
Re: Primavera integration task links
RiskyProject will import a schedule that has two tasks that are linked with both SS and FF relationships. However, because RiskyProject does not natively allow users to create these types of links, it will ignore one of the links.
Intaver Support Team
Intaver Institute Inc.