Modifying the number of hours or days make up days, weeks and months.
Moderator: Intaver Support
Modifying the number of hours or days make up days, weeks and months.
How can I adjust number of hours per day, days in month, and hours per week?
-
- Posts: 1018
- Joined: Wed Nov 09, 2005 9:55 am
Re: Modifying the number of hours or days make up days, weeks and months.
In the Project Options > Calendar tab you can define the number of hours/day, hours/week, and days/month.
To set as default values for all new projects, click the Set as default button.

To set as default values for all new projects, click the Set as default button.

Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Re: Modifying the number of hours or days make up days, weeks and months.
If I use schedule from Microsoft Project, does RiskyProject import this settings from the schedule, created in Microsoft Project?
-
- Posts: 1018
- Joined: Wed Nov 09, 2005 9:55 am
Re: Modifying the number of hours or days make up days, weeks and months.
Yes. It does.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com