Multiple Currencies
Moderator: Intaver Support
Multiple Currencies
You can only use a single currency for any single project. You can change currencies for different projects.
-
- Posts: 1008
- Joined: Wed Nov 09, 2005 9:55 am
Re: Multiple Currencies
You can only use a single currency for any single project. You can change currencies for different projects.
You can set the currency used for the project in the Project Options > Cost tab.
You can set the currency used for the project in the Project Options > Cost tab.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
-
- Posts: 1008
- Joined: Wed Nov 09, 2005 9:55 am
Re: Multiple Currencies
It is important to know that RiskyProject has only one currency for project portfolio (for RiskyProject Enterprise) and for whole project (for RiskyProject Lite and RiskyProject Professional). It may cause some incompatibility with Primavera P6 which uses multiple currencies.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com