Modifying the Incident Statistics view color scheme
Moderator: Intaver Support
Modifying the Incident Statistics view color scheme
We have set up the severity colors of the risk matrix, but the Incident Statistics view has not picked up our changes. Is there anyway to update the color scheme?
Jason
-
- Posts: 1008
- Joined: Wed Nov 09, 2005 9:55 am
Re: Modifying the Incident Statistics view color scheme
By default, the Incidents have the same number of classifications as the Risk Matrix. Yes, if you open the incidents tab, click Classifications. The Incident Classifications Settings dialog box opens.
Select the classification that you want to modify and click Define Color.
Select the color you want to apply and Click OK.
The classification color is updated and now appears in the view.
Select the classification that you want to modify and click Define Color.
Select the color you want to apply and Click OK.
The classification color is updated and now appears in the view.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com