Applying Risks to Consolidated Schedules
Moderator: Intaver Support
Applying Risks to Consolidated Schedules
Can risks be applied before and/or after a schedule has been consolidated?
-
- Posts: 1012
- Joined: Wed Nov 09, 2005 9:55 am
Re: Applying Risks to Consolidated Schedules
Risks should be applied after consolidation has been performed. If a risk is applied to a single activity prior to consolidation, it will be assigned with the same probability and impacts to a consolidated task and which may not be optimal.
Intaver Support Team