Isolating impact of Risk Events and Uncertainties
Moderator: Intaver Support
Isolating impact of Risk Events and Uncertainties
Is it possible to quickly separate the effects of uncertainties from risk events?
Business Development Manager
-
- Posts: 1008
- Joined: Wed Nov 09, 2005 9:55 am
Re: Isolating impact of Risk Events and Uncertainties
To Isolate the impacts of uncertainties you can disable all risks in the Risk ribbon.
To isolate the impact of uncertainties is more difficult. I would recommend making a copy of the file and then in the Project view, select all the activities, right click on the Activity number column (far left) and from the shortcut menu choose Set Low High Duration or Set Low High Cost.
In the dialog box, click the Set Lo, and High duration equal to base.
To isolate the impact of uncertainties is more difficult. I would recommend making a copy of the file and then in the Project view, select all the activities, right click on the Activity number column (far left) and from the shortcut menu choose Set Low High Duration or Set Low High Cost.
In the dialog box, click the Set Lo, and High duration equal to base.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com