Isolating impact of Risk Events and Uncertainties

This forum includes discussion about project risk analysis and risk management theory: Monte Carlo simulations, Event Chain Methodology, schedule and cost risk analysis. Please submit questions and case studies about your experience with our project risk analysis software.

Moderator: Intaver Support

Post Reply
Col
Posts: 19
Joined: Fri Mar 09, 2007 7:58 am
Location: Orlando, FL

Isolating impact of Risk Events and Uncertainties

Post by Col »

Is it possible to quickly separate the effects of uncertainties from risk events?
Business Development Manager
Intaver Support
Posts: 1008
Joined: Wed Nov 09, 2005 9:55 am

Re: Isolating impact of Risk Events and Uncertainties

Post by Intaver Support »

To Isolate the impacts of uncertainties you can disable all risks in the Risk ribbon.
Image

To isolate the impact of uncertainties is more difficult. I would recommend making a copy of the file and then in the Project view, select all the activities, right click on the Activity number column (far left) and from the shortcut menu choose Set Low High Duration or Set Low High Cost.
In the dialog box, click the Set Lo, and High duration equal to base.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Post Reply