Search found 76 matches
- Fri Jan 09, 2026 5:37 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Customizing anlaysis charts
- Replies: 1
- Views: 146
Customizing anlaysis charts
Is it possible to customize the charts that are shown in the Project Summary.
- Fri Jan 09, 2026 5:02 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Tasks Simulation Results buttons not appears.
- Replies: 1
- Views: 148
Tasks Simulation Results buttons not appears.
Hi,
I am doing an evaluation and cannot find the Task Simulation Results buttons on the Analysis toolbar, In fact, with the exception of the Result Gantt, none of the views shown online are there.
I am doing an evaluation and cannot find the Task Simulation Results buttons on the Analysis toolbar, In fact, with the exception of the Result Gantt, none of the views shown online are there.
- Fri Jan 09, 2026 4:44 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Viewing results in the test version
- Replies: 1
- Views: 54
Viewing results in the test version
Does the test version allow you see to results (s-curves and other charts)?
I am testing it right now, and when I click on the "results Gantt" on an activity bar, I don't get the s-curves and other results.
I am testing it right now, and when I click on the "results Gantt" on an activity bar, I don't get the s-curves and other results.
- Thu Dec 04, 2025 12:35 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Configuring Monte Carlo Simulations in RiskyProject
- Replies: 1
- Views: 7161
Configuring Monte Carlo Simulations in RiskyProject
Hey forum, I'm configuring the risk management system in RiskyProject Professional and need help with setting up Monte Carlo simulations. How do I enable distributions and set parameters
- Thu Dec 04, 2025 12:34 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Setting up the Risk Matrix
- Replies: 1
- Views: 3537
Setting up the Risk Matrix
Question for the community: In RiskyProject Professional, how do I configure the risk matrix for qualitative analysis? I want to customize the probability and impact ranges, colors, and make it nonlinear for better risk tolerance visualization. Tips appreciated!
- Thu Dec 04, 2025 8:28 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Customizing or Modifying risk categories
- Replies: 1
- Views: 3279
Customizing or Modifying risk categories
I'm new to RiskyProject Professional and trying to set up the risk management system for my project. How do I customize risk categories and impacts? The defaults like Duration and Cost are there, but I need to add a category for QHSE, can I combine some of the existing categories?!
- Mon Nov 03, 2025 11:18 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Schedule Diagnostics is frozen
- Replies: 1
- Views: 17398
Schedule Diagnostics is frozen
I am trying to apply the schedule diagnosis to a program with more than 5.000 lines and the software is getting stack. So I would like to know is there a way to solve this issue, or de diagnosis have a limit to work with a number of lines. I am going to try changing the extension of the file because...
- Thu Oct 23, 2025 3:40 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Schedule Diagnostics Freezing
- Replies: 1
- Views: 26360
Schedule Diagnostics Freezing
I am trying to apply the schedule diagnosis to a program with more than 5.000 lines and the software is getting stuck. So I would like to know is there a way to solve this issue?
- Wed Jul 16, 2025 7:41 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Mapping a single probability to each risk category.
- Replies: 1
- Views: 214489
Mapping a single probability to each risk category.
How do I map probability (cost, schedule, etc.) from my Excel risk register. We only have one probability, where as RiskyProject has probabilities for each risk category. Also, how do I add the cost of the pre-mitigated risk?
- Tue Nov 12, 2024 11:03 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Importing Risk Registers into an existing schedule
- Replies: 1
- Views: 184877
Importing Risk Registers into an existing schedule
Getting odd results after importing a risk register and assigning risks. I can provide the files if you have any suggestions on what might be going on.
- Fri Sep 06, 2024 2:14 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Trial period expired prior to evaluation
- Replies: 1
- Views: 178388
Trial period expired prior to evaluation
I wasn't as prepared to use the trial as I thought and could not demo the software properly. Is it possible to extend the trial period now that I am in a better place to do a proper demo?
- Fri Dec 15, 2023 9:06 pm
- Forum: Project Portfolio Risk Management
- Topic: Incorrect username or password error message logging onto database
- Replies: 1
- Views: 191919
Incorrect username or password error message logging onto database
We are having an issue with user authentication in RiskyProject Enterprise. Some users when having not logged onto the system for a couple of months the get an error message “Incorrect username or password”. In addition, we have users who can logon without having to enter their username and password...
- Fri Dec 15, 2023 9:05 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Inserting new columns to the Risk Register
- Replies: 1
- Views: 190781
Inserting new columns to the Risk Register
I would like to insert a custom column "Risk Velocity" to the risk register. Is it possible to do it? I could not find this field within a list of standard fields in RiskyProject.
- Sun Oct 15, 2023 8:21 pm
- Forum: Project Portfolio Risk Management
- Topic: Adding Incidents
- Replies: 1
- Views: 192062
Adding Incidents
We are thinking of adding Incident management to our processes. How should we go about it?
- Sun Oct 15, 2023 8:21 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: How to Enable Incidents
- Replies: 1
- Views: 191844
How to Enable Incidents
We just purchased RiskyProject Enterprise and noticed that there is Incident management in the Help. However, we have not been able to find it. Is this a separate module that we need to purchase, if not is can we enable somehow?