You can also new Risk Information dialog for risk assignments:
- double click on Task ID in any task view
- go to Risks tab
- update risk assignment, alternatives, probabilities, outcome and moment of risk
Search found 999 matches
- Sun Jun 09, 2024 6:25 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Updating Risk Assignments
- Replies: 2
- Views: 10553
- Mon May 13, 2024 2:48 pm
- Forum: Project Portfolio Risk Management
- Topic: Can Deadline be used to automatically adjust schedules
- Replies: 1
- Views: 10171
Re: Can Deadline be used to automatically adjust schedules
With deadlines the results will only show that it fails to meet the deadline. It does not compress the schedule as you would like. Typically, schedule compression or acceleration requires a complete rework of the schedule including adding additional resources, more parallel activities. etc as requir...
- Mon May 13, 2024 2:46 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Calculated risk probability is different that the Input Probability
- Replies: 1
- Views: 7479
Re: Calculated risk probability is different that the Input Probability
Calculated probability can vary from the input. But normally not by much. The reason is similar to throwing a dice. At each iteration, the risk has a 15% of occurring, so after 1 iteration, the probability will be 0 or 100%, after 2 0,30, or 100%. After 100 iterations, it could occur 15x (ie 15%) bu...
- Mon May 13, 2024 2:44 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Using resources to model a schedule and cost risk
- Replies: 1
- Views: 7367
Re: Using resources to model a schedule and cost risk
If you model a schedule risk with resources with rates allocated to the affected tasks. The added costs due to the risk will be part of the analysis. Same as if you apply the risk directly to the resource, however if that resource is assigned to any other tasks, they will be affected as well.
- Wed Apr 10, 2024 6:04 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Calculated risk probability is different than assigned probability.
- Replies: 1
- Views: 4477
Re: Calculated risk probability is different than assigned probability.
Calculated probability can vary from the input. But normally not by much. The reason is similar to throwing a dice. At each iteration, the risk has a 15% of occurring, so after 1 iteration, the probability will be 0 or 100%, after 2 throws 0,50, or 100%. After 100 iterations, it could occur 15x (ie ...
- Wed Apr 10, 2024 6:02 pm
- Forum: Project Portfolio Risk Management
- Topic: Assigning Risks to Tasks with Resource Costs
- Replies: 1
- Views: 5774
Re: Assigning Risks to Tasks with Resource Costs
If you model a schedule risk with resources allocated to the affected tasks. The added costs due to the increased time due the risk will be calculated based on the resource rate and will be part of the analysis. You can also model this by you apply the risk directly to the resource, however if that ...
- Wed Apr 10, 2024 5:59 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Automatically adjusting schedules using Latest Project Deadline
- Replies: 1
- Views: 5785
Re: Automatically adjusting schedules using Latest Project Deadline
With deadlines the results will only show that it fails to meet the deadline. It does not compress the schedule as you would like. Typically the schedule compression or acceleration requires a complete rework of the schedule including adding additional resources, more parallel activities. etc as req...
- Wed Mar 20, 2024 10:14 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Copying the Default Risk Properties for Review
- Replies: 1
- Views: 5286
Re: Copying the Default Risk Properties for Review
They can do this in the Default Properties view selecting all of the properties, and copy using the shortcut menu. This list can then by pasted into a spreadsheet or document for review.
![Image](https://www.intaver.com/images/RP_Forum_CopyProp.png)
![Image](https://www.intaver.com/images/RP_Forum_CopyProp.png)
- Wed Mar 20, 2024 10:10 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Low number of Sensitivity Results
- Replies: 1
- Views: 4206
Re: Low number of Sensitivity Results
Best Practice: Setting Sensitivity Coefficient Threshold There is a threshold that can be set for viewing sensitivity results, where any results that do not meet the sensitivity coefficient threshold are not show as way to simplify the analysis of schedules. If you many activities with similar level...
- Wed Mar 20, 2024 10:03 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Sorting Risk Assignments view
- Replies: 1
- Views: 3766
Re: Sorting Risk Assignments view
The Risk Assignment view doesn't sort and the Risk ID is not one of the data fields available. The Assignment view is listed alphabetically. But the Risk Register you can list Alphabetically as well using the buttons at the top left of the Register view so that they are listed in the same order as R...
- Fri Feb 09, 2024 11:03 pm
- Forum: Project Portfolio Risk Management
- Topic: Where is the End User License Agreement
- Replies: 1
- Views: 5976
Re: Where is the End User License Agreement
We do include the EULA as part of the installation Wizard, which must be accepted prior to installation of the software. An example is shown below. https://www.intaver.com/images/RP_Forum_EULA.png It is also available as part of the installation package. You can also request a copy of the current EU...
- Fri Feb 09, 2024 10:58 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Low number of iterations
- Replies: 1
- Views: 4580
Re: Low number of iterations
The number of iterations that will be run is set in the Project Options > Calculations tab. Based on the number of iterations you are seeing, convergence is enabled. Convergence occurs when the simulation results equal the mean and standard deviation values that are defined. To run a higher number o...
- Fri Feb 09, 2024 10:55 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Updating file causing short delays
- Replies: 1
- Views: 5079
Re: Updating file causing short delays
RiskyProject has 2 default calculation settings: Deterministic and Probabilistic. When Probabilistic is selected, RiskyProject has an algorithm in which it monitors the size of the data and available computer resources and if it calculates that it can run it in one second it will run a simulation. I...
- Thu Jan 11, 2024 6:45 pm
- Forum: Project Portfolio Risk Management
- Topic: Setting the height of rows
- Replies: 1
- Views: 6925
Re: Setting the height of rows
Our current Risk Register does not support wrapping text.
Normally the extra width is due to non-breaking spaces or other formatting in the Excel. To resize, hover over the row border and left-click which will change to cursor so that you can drag the row border to the width you require.
Normally the extra width is due to non-breaking spaces or other formatting in the Excel. To resize, hover over the row border and left-click which will change to cursor so that you can drag the row border to the width you require.
- Thu Jan 11, 2024 6:43 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Legacy MSP xml format error message
- Replies: 1
- Views: 5678
Re: Legacy MSP xml format error message
You probably see the following message: https://www.intaver.com/images/RP_Forum_XMLMSG.png As of 2019, the xml generated by earlier versions of MSP and RiskyProject are considered “Legacy” formats, which can cause these types of errors, though they do not happen consistently. To allow the use of old...