Search found 4 matches
- Fri Aug 21, 2026 12:50 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: MSP Auto-Calculation Disabled When Running RiskyProject Add In
- Replies: 1
- Views: 4302
MSP Auto-Calculation Disabled When Running RiskyProject Add In
We’re evaluating RiskyProject and have run into an issue with the MSP add in. After installing RiskyProject, Microsoft Project’s scheduling engine appears to stop working correctly. All dependencies are ignored and tasks become locked to the project start date. After some testing, I found that each ...
- Fri Oct 19, 2007 5:57 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Work calculation in RiskyProject
- Replies: 3
- Views: 42364
Work calculation in RiskyProject
I'd like to be able to see amount of work (number of man hours) for the particular resource. For example, this particular resource will spend 50 hours this week on this activity. Can I do it in RiskyProject?
- Wed Nov 01, 2006 12:07 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Import Calendar from MS Project
- Replies: 4
- Views: 385162
- Thu Oct 19, 2006 1:15 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Import Calendar from MS Project
- Replies: 4
- Views: 385162
Import Calendar from MS Project
I found that calendar I imported from MS Project is different in RiskyProject. The shift supposes to start at 8:30 in MS Project, but after import it starts at 8:00 in RiskyProject. As a result my schedule in RiskyProject it a little bit off.