Assigning Risks to Tasks with Resource Costs
Posted: Wed Apr 10, 2024 6:01 pm
Looking for some help on how to model risks with resources. I have a task that runs for 3 months, with a resource or resources assigned at 100% for the duration of the task. I have a time delay risk that has a 15% of causing a 10% delay to that task. I want to show an extension of time to that task and then any affecting it in the triangular distribution on the result gantt, but then also an extension of time required from the resource working extra due to the extended time and therefore an increase in cost. How do I go about doing this?