RiskyProject risk form

General discussion and questions about project risk management and risk analysis software RiskyProject. Includes discussion on how to perform efficient project risk analysis using our software.

Moderator: Intaver Support

Post Reply
Tomico
Posts: 63
Joined: Thu May 18, 2006 5:02 pm
Location: Naples, FL

RiskyProject risk form

Post by Tomico »

Is it possible to customize risk form (double click on risk ID) within a risk register? I have few items I would like to track.
Intaver Support
Posts: 1012
Joined: Wed Nov 09, 2005 9:55 am

Re: RiskyProject 4.2 risk form

Post by Intaver Support »

You cannot change a layout of risk form (Properies tab in Risk Information dialog box). However you add any custom properties to be displayed in the Custom tab of the the same dialog box. To do it:
1. Go to Risk->Settings->Default Properties
2. Enter enty property and define type of this properties (number, string, etc.)
3. Go to Risk Register
4. Enter value for this property in Custom tab of Risk Information dialog box
You may now display and search risks in risk register based on this new property.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Tomico
Posts: 63
Joined: Thu May 18, 2006 5:02 pm
Location: Naples, FL

Re: RiskyProject 4.2 risk form

Post by Tomico »

I downloaded RiskyProject 5. It has a lot of nice features. Thanks. What I would like to do is to define action items for mitigation plans and be able to report in it. How to do it RiskyProject 5?
Intaver Support
Posts: 1012
Joined: Wed Nov 09, 2005 9:55 am

Re: RiskyProject risk form

Post by Intaver Support »

Each mitigation plan and mitigation plan assignments have notes. These notes are your action items. When you assign mitigation plan to risk, just fill out notes for each assignment.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Tomico
Posts: 63
Joined: Thu May 18, 2006 5:02 pm
Location: Naples, FL

Search risk register

Post by Tomico »

I created a custom risk property: "Material requirements". Is it possible to search risk register register to find all risks, where material requirements is greater then from example $5000?
Intaver Support
Posts: 1012
Joined: Wed Nov 09, 2005 9:55 am

Re: RiskyProject risk form

Post by Intaver Support »

When you in risk register click on Filter button on the left hand side. It will allow you to perform search of the risk register. For example, you select property "Material requirements", define condition (>) and enter value ($3000).
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Post Reply