Risk Scoring Options

This forum includes discussion about project risk analysis and risk management theory: Monte Carlo simulations, Event Chain Methodology, schedule and cost risk analysis. Please submit questions and case studies about your experience with our project risk analysis software.

Moderator: Intaver Support

Post Reply
Jason
Posts: 38
Joined: Wed Nov 09, 2005 10:46 pm

Risk Scoring Options

Post by Jason »

Which risk scoring method should I use?
Jason
Intaver Support
Posts: 1012
Joined: Wed Nov 09, 2005 9:55 am

Re: Risk Scoring Options

Post by Intaver Support »

This answer will focus on the two risk scoring methods available in the Format Risk > Advanced Settings dialog pictured below.

Image

The two risk scoring methods are:
Method 1 - Combined impact: maximum impact of all categories, and
Method 2 - Combined impact: sum of impacts in each category and then normalized.
So what is the difference? Let’ s take a look at a simple example for the same risk using the standard 1-5 assessments for probability and impact, where 1 is lowest and 5 is highest.

Image

What we can see is that with the scoring method 1, the Risk score does not change even though impacts to the Schedule and Performance are significantly higher. Whereas, scoring method 2 incorporates the assessment for all impacts and provides a scores that reflects the overall impact of the risk.
For quantitative risk assessments, we always recommend Method 2 as it provides a more accurate assessment and therefore ranking and prioritization of the risk.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Post Reply