How do I see the % of time (across iterations) that a particular task is on the critical path (“% criticiality”)?
-
- Posts: 1012
- Joined: Wed Nov 09, 2005 9:55 am
Re: Criticality Index
1. Turn on the critical path calculation. This will impact performance as CP requires both a forward and backward pass through the schedule. Here is how to do this RiskyProject Help Content (intaver.com)
2. Add the criticality index column to the Result Gantt view.