Cost of risk is too high
Moderator: Intaver Support
-
- Posts: 25
- Joined: Tue Dec 18, 2007 3:39 pm
- Location: USA, MI
Cost of risk is too high
I have project where the “cost of risk” values seem to high. For example, consider the risk below. There is an 25% chance that it will cost $5000. After a run, it appears that I have to make a risk reservation of 11,052. Or do I have to work it out differently?
Project Engineer
-
- Posts: 1005
- Joined: Wed Nov 09, 2005 9:55 am
Re: Cost of risk is too high
If this is happening when the risk is assigned to a single task, I suspect that the activity has a resource with a rate associated with it as well. When you have a schedule risk assigned to a task with a resource rate this will also generate "time dependent" costs.
Here is how this works.
Fixed cost risk to a single task 5 days:
Here are the results:
Create a resource with a rate of $100/hr:
Add the time delay risk:
Run a Simulation.
The results are now. The majority of the cost risk is due to the schedule increase.
Here is how this works.
Fixed cost risk to a single task 5 days:
Here are the results:
Create a resource with a rate of $100/hr:
Add the time delay risk:
Run a Simulation.
The results are now. The majority of the cost risk is due to the schedule increase.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com