Importing Risk Registers into an existing schedule
Moderator: Intaver Support
Importing Risk Registers into an existing schedule
Getting odd results after importing a risk register and assigning risks. I can provide the files if you have any suggestions on what might be going on.
Ken the PM
-
- Posts: 1015
- Joined: Wed Nov 09, 2005 9:55 am
Re: Importing Risk Registers into an existing schedule
Check the file and noticed that there are a lot of global risks many of which are assigned to activities that have local task risks. When you import a risk register there is no task assignments, so by default the risks are set as global. However if the risk is global and local at the same time this will cause double counting. If you are going to use this method, I recommend doing a quick visual check in the Risk Assignment view to remove these.
To delete the global risk assignment, right-click on it and in the shortcut menu, click Delete Risk Assignment.
To delete the global risk assignment, right-click on it and in the shortcut menu, click Delete Risk Assignment.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com