Importing Risk Registers into an existing schedule

This forum containts questions about RiskyProject project risk analysis and risk management software: features, issues, problem reports. If you have any problems or question, please submit it here.

Moderator: Intaver Support

Post Reply
Ken
Posts: 67
Joined: Wed Nov 09, 2005 9:47 am
Location: California

Importing Risk Registers into an existing schedule

Post by Ken »

Getting odd results after importing a risk register and assigning risks. I can provide the files if you have any suggestions on what might be going on.
Ken the PM
Intaver Support
Posts: 1015
Joined: Wed Nov 09, 2005 9:55 am

Re: Importing Risk Registers into an existing schedule

Post by Intaver Support »

Check the file and noticed that there are a lot of global risks many of which are assigned to activities that have local task risks. When you import a risk register there is no task assignments, so by default the risks are set as global. However if the risk is global and local at the same time this will cause double counting. If you are going to use this method, I recommend doing a quick visual check in the Risk Assignment view to remove these.

Image

To delete the global risk assignment, right-click on it and in the shortcut menu, click Delete Risk Assignment.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com