How does RiskyProject handle task slippage
Moderator: Intaver Support
How does RiskyProject handle task slippage
Does Risky Project factor in a tasks slippage into its analyses? I.e. if a task has a baseline duration of 200 days, a deterministic duration of 400 days, but the remaining duration is triangularly distributed to be 1 day, 2 days, and 3 days, does RP factor in the fact the task has significantly slipped even though the loaded distributions have a minimal range?
-
- Posts: 1027
- Joined: Wed Nov 09, 2005 9:55 am
Re: How does RiskyProject handle task slippage
If the task isn't completed, then RiskyProject prorates the distribution based on the % complete unless you override this manually by added low, most likely, and high remaining durations in the Tracking tab of Task Information dialog.


Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com