How can a present P10 and P90 percentiles on frequency and cumulative probability plots in RiskyProject?
Intaver Support
Posts: 1012
Joined: Wed Nov 09, 2005 9:55 am

Re: P10 and P90 percentiles on frequency historgrams

Post by Intaver Support »

In current version of RiskyProject for each frequency and cumulative probability plots we have a slider at the top of the bar. You can move this slider and see a probability associated with certain value. For example, you can see that there is a 60% chance that project of task will be completed in 20 days. This way you can see value associated with P10 or P90. In next versions in addition to this slider we are going to how line associated with particular probability, such P10 and P90. It will be separate lines independent of slider, so slider will remain as it is.

You have an options to enable/disable this slider. To do it just right click on the chart and selection options. Format Chart dialog box will come up. You can check or uncheck option "Slider". The chart will be re-drawing with or without this slider.