Calendar Exceptions

Post by NTT »

I have calendar exception in MS Project (holidays). Will they be imported to RiskyProject if I use RiskyProject Addin or XML export?
risk manager
Intaver Support
Posts: 1012
Joined: Wed Nov 09, 2005 9:55 am

Re: Calendar Exceptions

Post by Intaver Support »

Quick answer is yes. Call calendars in the MS Project schedule including resources and task calendars are included when you import using either the Addin or xml.
You can check to ensure you calendars have imported correctly in the Working Time dialog box. Select the calendar from the drop-down list and exceptions will be marked accordingly.

Image
Intaver Support Team
Intaver Institute Inc.