Integration with Asta PowerProject
Moderator: Intaver Support
-
- Posts: 1012
- Joined: Wed Nov 09, 2005 9:55 am
Re: Integration with Asta PowerProject
Yes. Both Asta PowerProject and RiskyProject support MSP xml. Therefore you can save your PowerProject file in one of these formats and import into RiskyProject using the File>Import> <file type> command.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
-
- Posts: 1012
- Joined: Wed Nov 09, 2005 9:55 am
Re: Integration with Asta PowerProject
We have many clients who asked as did we actually tried to performed risk analysis based on schedules created in Asta Powerproject. Yes. We tried many schedules created in Asta and import them to RiskyProject. Asta and RiskyProject are compatible with each other. You can use both XML export from Asta and XER (Oracle Primavera format) export. The process of export schedule from Asta and import it in RiskyProject is fast and easy.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com