Pre and Post Mitigation scores after MC Simulation
Posted: Wed Jan 15, 2025 2:35 pm
I added mitigations to each of my risks, and noticed there are pre-mitigation and post-mitigation tables on the Risk Register view.
When I run the Monte Carlo analysis, is it assuming mitigation for only those that have already been met based on mitigation date, or is it assuming all mitigations will happen even if they have not yet happened?
If the Monte Carlo analysis I run today does not include mitigations that have not yet happened, is there a way to run an analysis today that will show what will happen if all mitigations are successful in the future?
When I run the Monte Carlo analysis, is it assuming mitigation for only those that have already been met based on mitigation date, or is it assuming all mitigations will happen even if they have not yet happened?
If the Monte Carlo analysis I run today does not include mitigations that have not yet happened, is there a way to run an analysis today that will show what will happen if all mitigations are successful in the future?