Cost of risk is too high
I have project where the “cost of risk” values seem to high. For example, consider the risk below. There is an 25% chance that it will cost $5000. After a run, it appears that I have to make a risk reservation of 11,052. Or do I have to work it out differently?
- Sat Jul 27, 2024 6:34 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Updating risks during project execuition due to mitigation efforts
- Replies: 1
- Views: 16997
Updating risks during project execuition due to mitigation efforts
How should I update risks in when miti during the project when certain measures have been implemented and the risks in terms of probability and impact have been reduced . Should I create a baseline 1 and then adjust the probability and impact in Pre-Mitigation to reflect the current value of the ris...
- Mon Aug 07, 2023 12:13 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Assigning a multiday delay to a one day task
- Replies: 1
- Views: 14246
Assigning a multiday delay to a one day task
I have a risk that that the Site Handover might get delayed even with 2 weeks. If I want to simulate this/ I can set a relative delay even with 85% probability and 70% percent outcome, but the program considers the duration of the task and not the start date of the task. How can I set up that the pr...
- Wed Aug 26, 2020 5:11 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Setting Chart defaults
- Replies: 2
- Views: 30661
Setting Chart defaults
Is there a place where you can set chart default settings? From what I can see charts settings can only be set for each project and they do not apply to new projects, that is they go back to the defaults when you first install the software.
- Tue Jun 23, 2020 3:10 pm
- Forum: Project Portfolio Risk Management
- Topic: Progress report
- Replies: 1
- Views: 27490
Progress report
Can the RiskyProject Enterprise do a Progress report, indicating slippage, scope growth and progress to date. I see you do have progress dashboard and was wondering how this could be formatted (by myself) for reporting.
- Wed Apr 22, 2020 4:51 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Exporting RiskyProject results to Primavera P6
- Replies: 1
- Views: 26842
Exporting RiskyProject results to Primavera P6
Is any way to export results of RiskyProject risk analysis back to Primavera P6?
- Wed Apr 22, 2020 4:40 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Unique Task IDs After Import from Primavera P6
- Replies: 1
- Views: 26697
Unique Task IDs After Import from Primavera P6
RiskyProject doesn’t seem to bring over the unique Activity IDs that we have in Primavera P6. We have this problem using both XML import and Primaveta XER import.
- Sat Feb 22, 2020 5:46 pm
- Forum: Project Portfolio Risk Management
- Topic: Saving Results to Baselines
- Replies: 1
- Views: 31219
Saving Results to Baselines
There is not an option to select probabilistic data baseline. Even after disabling risks and uncertainties. Only options given are deterministic, low, base, high and results based on percentile.
- Sat Feb 22, 2020 5:36 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Generating Risk Adjusted Margins
- Replies: 1
- Views: 29839
Generating Risk Adjusted Margins
We have been asked to calculate schedule margin activities based on p80. How do can I calculate this in RiskyProject?
- Sat Feb 22, 2020 5:27 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Export Results of Analysis
- Replies: 1
- Views: 30047
Export Results of Analysis
How to export the analysis results as a csv file?
- Fri Jan 31, 2020 7:09 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Creating post mitigated schedules
- Replies: 1
- Views: 29651
Creating post mitigated schedules
We added a mitigation plan a risk, but it does not seem to impact the results of our analysis.
- Thu Sep 13, 2018 11:24 am
- Forum: Project Portfolio Risk Management
- Topic: Impact and Risk Scores equal Zero
- Replies: 1
- Views: 30002
Impact and Risk Scores equal Zero
In RiskyProject Enterprise I have loaded our 4 primary Risks into the schedule and linked them s to various tasks When looking at our risk register, 3 of the 4 risks have 0.0% Impact and 0.0% Score.
- Thu Sep 13, 2018 11:23 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: What are the Legends?
- Replies: 1
- Views: 17972
What are the Legends?
I was reading through your documentation and there was a reference to Legends. However, I do not see them on my screen.
- Thu Sep 13, 2018 11:22 am
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: What default setting should I have for the moment of Risk?
- Replies: 1
- Views: 21033
What default setting should I have for the moment of Risk?
What does the statistical distribution for moment of risk in the Project Options > Risk tab refer to and how should I set it?
- Fri Jul 13, 2018 4:03 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: How do tasks and task deadlines affect task success rates
- Replies: 1
- Views: 20859
How do tasks and task deadlines affect task success rates
Are the task success rates only affected by deadlines, or are there any other conditions which can affect it?