I have a risk that that the Site Handover might get delayed even with 2 weeks.
If I want to simulate this/ I can set a relative delay even with 85% probability and 70% percent outcome, but the program considers the duration of the task and not the start date of the task. How can I set up that the program can simulate 1-2 weeks possible delay of 1 day activities? It went up only to 1,7 days.
Assigning a multiday delay to a one day task
Moderator: Intaver Support
-
- Posts: 25
- Joined: Tue Dec 18, 2007 3:39 pm
- Location: USA, MI
Assigning a multiday delay to a one day task
Project Engineer
-
- Posts: 1018
- Joined: Wed Nov 09, 2005 9:55 am
Re: Assigning a multiday delay to a one day task
You would need to use Fixed Duration Delay (5 to 10 days) rather than Relative Delay. It is possible to model a 500% - 1000% relative delay as well.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com