Defaults for risk mitigation and response plans

Posted: Sun Sep 20, 2015 10:58 am
by BusinessDecisions
Every time I add a mitigation activity to the waterfall chart, it seems to automatically decrease the impact by 5% which I don’t want. It looks like a default but I don’t see any setting in the options.

Re: Defaults for risk mitigation and response plans

Posted: Mon Sep 21, 2015 10:14 am
by Intaver Support
When you are creating your risk mitigation plans in the mitigation waterfall chart, each activity that you add to the risk mitigation waterfall chart automatically is added as a mitigation plan or activity in the Mitigation/Response view. Each of these steps represents a planned activity which will change either the probability and/or impact of a risk, which in turn lowers the risk score. RiskyProject has hardcoded default values for reducing probability and impact (5%). If you do not modify these values, they are automatically added to the waterfall chart. You can set these default values in advance if you add the plans to the Mitigation/Response View. The default values can be added to the Risk Probability Reduction and Risk Impact Reduction fields for each plan.

Image