Rtgorwer
Posts: 21
Joined: Wed Jan 10, 2007 4:10 pm
Location: France

Multiple Currencies

Post by Rtgorwer »

You can only use a single currency for any single project. You can change currencies for different projects.
Intaver Support
Posts: 1002
Joined: Wed Nov 09, 2005 9:55 am

Re: Multiple Currencies

Post by Intaver Support »

You can only use a single currency for any single project. You can change currencies for different projects.
You can set the currency used for the project in the Project Options > Cost tab.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Support
Posts: 1002
Joined: Wed Nov 09, 2005 9:55 am

Re: Multiple Currencies

Post by Intaver Support »

It is important to know that RiskyProject has only one currency for project portfolio (for RiskyProject Enterprise) and for whole project (for RiskyProject Lite and RiskyProject Professional). It may cause some incompatibility with Primavera P6 which uses multiple currencies.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com