Assigning a mitigation or risk response plan to a
task
Before you can assign a mitigation or risk response plan to a task,
you must create it in the Mitigation or Response view. These
mitigation plans can be executed when a risk occurs.
1. On the Workflow bar, click the Risks
tab and then the Risk Register
view.
2. Double-click the risk to which you want to link the mitigation or
response plan.
3. Click the Assign to tasks or resources tab.
4. If the risk is not already assigned to a task, you must assign
the risk to the task (s).
5. Click the task to which you want to assign the plan.
6. On the Selected assignment:
table, select Execute Response Plan as the
Outcome for the risk. The Result field will now list all
available response plans.
7. Select the response plan from the Result list.
8. Repeat steps 4-6 if you want to assign the plan to additional
tasks.
You may use any risk assignment view or dialog to assign a
mitigation and response plan to a risk.
See
also
Analyzing Risk Mitigation Efforts with Multiple Baselines
Comparing pre and post-mitigation baselines
Converting a baseline to a current schedule
Creating a mitigation or risk response plans
|