Creating a baseline

Once you have run a simulation on your project, you can save the results as a baseline.
1. On the Tools menu, choose Create or Update Baseline.
2. Enter a name for the baseline. By default, it is assigned “Baseline #_”
3. Select the type of results (Low, Base, High, specific percentile, or Deterministic) that you want to use for your baseline.
4. Click OK.
5. If you are using probabilistic results for the baseline, you are prompted to disable all risks and uncertainties from the schedule.
    •  Choosing Yes will in effect create a deterministic baseline out of the results you selected.
    •  Choosing No will mean that all risks and uncertainties will remain. If you calculate this baseline again, this may cause a double count of the risks and     uncertainties.

See also

Analyzing Risk Mitigation Efforts with Multiple Baselines

Comparing pre and post-mitigation baselines

Converting a baseline to a current schedule

Creating a mitigation or risk response plans