Setting the current baseline

The current baseline is the project data that appears in RiskyProject. You can change current baselines as part of you planning efforts.

  1. Click the Schedule tab. In the Baselines group, click Manage.
  2. Select the check box beside a baseline to set it as the Current Baseline.
  3. Enter a name for the baseline. By default, it is assigned "Baseline #_".

Right click on a baseline to copy baseline data to the clipboard or delete it.


See also

Creating a baseline

Analyzing Risk Mitigation Efforts with Multiple Baselines

Comparing pre and post-mitigation baselines