Search Help:

Frequently Asked Questions

What is the difference between qualitative and quantitative risk analysis in RiskyProject?

If you do not have a schedule for your project, RiskyProject will only perform qualitative risk analysis. However, if you add a schedule by either adding activities or importing a schedule, RiskyProject automatically switches to quantitative analysis. You may switch between qualitative and quantitative analysis by adding or removing a project schedule.

How do I assign risks to tasks?

You can assign risks to task using four methods in RiskyProject.

  1. Risk Drag & Drop View: this is the preferred method for project risk assignment. You simply select one or many risks on the left page and drop them on the task.
  2. Risk Register: if you are using the Risk Register, you can assign a risk and mutually exclusive risk alternatives to tasks by double-clicking on the risk in the risk register and assigning tasks to the risk in the Assign to tasks or resources tab.
  3. Risk Assignment View: double-click on a risk ID in Risk Assignment view and use the Risk Assignment Information dialog to re-assign risks to task or resources or make them global.
  4. Risk Tabs on Task Information and Resource Information Dialog boxes: you can create and assign local risks to a task using this method. This is the preferred method if you want to assign a few different risks to separate tasks or resources.

How should I use the risk register?

You should use the risk register as the central place to define your project’s risk breakdown structure. Once you have added the risks, from the risk register you can:

  • Add risk properties (date created, recorder, owner, etc.).
  • Assign risks to tasks and resources.
  • Sort and filter risks.
  • View risk status, including results of mitigation efforts. Risks can be opened and closed, risk and issues, or threats and opportunities.

When should I correlate risks and how do I do it?

Risk correlations are useful when the two risks are likely to occur together. For example, the risk "bad weather" is correlated with the risk "late delivery of materials". You can create risk correlations in the Correlations tab of the Risk Information dialog box in the Global and Local risks views, as well as risk tabs for tasks and resources.
RiskyProject uses only strong correlation between risks. If Risk 1 has chance of occurrence is 10% and Risk 2 chance of occurrence is 20% and both risks are correlated, Risk 1 will always occur when Risk 2 occurs, but Risk 2 may occur when Risk 1 does not occur.

How are risk probabilities, impacts, and scores calculated?

Risk probabilities, impacts, and scores are calculated the following way:

  • RiskyProject tracks impact on each risk on different project parameters for each iteration of Monte Carlo simulations. It is done is absolute units. For example, in first iteration Risk A caused delay 2 days.
  • RiskyProject also calculates duration, cost, success rate, finish time, and work on each iteration.
  • RiskyProject calculates the Spearman Rank Order correlation coefficient between duration impact for each risk and project duration. This coefficient is presented in Sensitivity view.
  • Correlation coefficients are not yet a risk impact. They only show how the risk affects the project. If a correlation coefficient is low, and the risk is not correlated with duration, it means than some other factors affect duration other than this risk. To become an impact, the correlation coefficient must be normalized. For example, you have a schedule, which has only one risk with an outcome of an increase in duration of 2 days. The correlation coefficient will be 100% because the schedule does not have any other uncertainties. Now change the risk outcome to 100 days. The correlation coefficient again will be 100%. Risk impact takes into account absolute value of duration increase, cost increase, etc. If the duration increases 2 times when compared with the original project schedule, the normalization coefficient is 1. Otherwise, the normalization coefficient will be greater or less than 1. Impact equals correlation coefficient multiplied with the normalization coefficient.
  • Risk probability calculated based on chance of risk on for each assignment. If risk has only one assignment, calculated probability equals input chance. If the risk has multiple assignments which as not mutually exclusive alternative, the probability is calculated by combining risk results of each iteration as shown in the example:

Risk probability and impact

Combined probability will equal 80%

  • Risk score equals probability multiplied by impact.
  • For risks affecting All Parameters (combination of duration, cost, safety, quality, etc.) calculated impact is calculated using impact for each risk category, multiplied on relative importance of risks for this category. For schedule related risk categories risk impact on finish time and success rate will not be used to calculate risk impact. For schedule related risk categories, the risk impact on finish time and success rate will not be used to calculate risk impact. This relative importance can be seen on the Risk Outcomes (Risk menu).

How can I update a project schedule from Microsoft Project and keep my assigned risks?

You may use the RiskyProject toolbar or ribbon in Microsoft Project to transfer a schedule from Microsoft Project to RiskyProject. When you use the RiskyProject toolbar or ribbon, your schedule in Microsoft Project will be associated with risks and uncertainties defined in RiskyProject.

When you import (click Import on the File menu) an updated schedule from Microsoft Project, RiskyProject gives you the option of completely overwriting the existing schedule or updating the existing schedule with new data in Microsoft Project, while retaining global and local risk assignments. This is useful if you originally exported the schedule and assigned risks to the project. RiskyProject keeps unique task IDs from Microsoft Project.

How do I rank schedule related and non-schedule risks together?

RiskyProject calculates the relative impact of both schedule-related and non-schedule risks in such a manner as to provide a valid comparison of both types of risks in regards to potential impact on the project. The basis of this comparison is the relative weight (importance) that you assign to each risk category. You can view the impact (threat or opportunity) of each risk in the Risk Matrix view and Risk Register view. In the Risk Tabs of Task Information dialog box and Resource Information dialog box you will find an impact of the risk on all parameters under “All” (Calculated impact on all project parameters) column.

How do I plan a risk response?

Risk response planning is done in the Mitigation or Response view on the Risk workflow. Risk responses are activities that will occur in a risk occurs. These activities can be modeled in a similar manner as a risk with an outcome and result. Risk Mitigation and Response view can be useful, if you have many risks causing the same response.

You assign the risk response to a risk as a risk outcome "Execute Response Plan" and the response plan as the result.

For example, you have two risks "Problem with supplier" and "Problem with the component" that will initiate the same response "Replace Component". If you define "Replace Component" and assign it to both risks using the risk outcome "Execute Response Plan", the response plan will be executed only once even if both risks occur together.

How can I compare mitigation efforts using different baselines?

There are two methods to view the results of your mitigation planning against the original schedule. To compare the results, first create a baseline using the results from the original schedule. Model the planned mitigation efforts in your current schedule taking into account any additional activities and costs that the mitigation efforts will entail (these may also introduce additional risks)

In the risk register, use the Configure Pre and Post Mitigation button to select the original baseline as the pre-mitigation and the current schedule as the post-mitigation. The risk register will display the risk impact and score of each risk for the pre and post mitigation schedules.
In the Manage Baselines dialog box, you can compare major project parameters of the two schedules: Duration, Finish Time, Cost, and Success Rate.

How many iterations are required in a simulation?

The number of iterations required depends upon the risks you have assigned to the project. Normally, the minimum number of iterations is 200 and can be adequate on small, non-strategic projects. However, if you have risks that have a very low chance of occurring, but have a potential large impact, the results will not account for this risk unless you run sufficient simulations. For example, your project has a 0.5% chance of being cancelled due to political instability. You must run at least 200 iterations, just to ensure just to ensure that the simulation runs a single occurrence of this risk. To adequately model these types of risks, we recommend a minimum of 600 simulations.

When should I use a risk event instead of a statistical distribution?

RiskyProject supports both methods of risk analysis. Statistical distribution or uncertainty modeling is recommended in projects where there is strong and analogous historical data that is supported by expert opinion.
If this data does not exist, risk event modeling will normally result in a more accurate assessment of your project risk and uncertainty. In addition, risk events make it much easier to identify critical risks through sensitivity analysis as most if not all uncertainty in a project is caused by risk events. Without risk event modeling, you will need to do a root cause analysis to identify which risks are causing the uncertainty in your project.

What are mutually exclusive alternatives for risks and how are they calculated in RiskyProject?

Mutually exclusive alternatives are used to calculate alternate outcomes for the same risk event that cannot occur at the same time. An alternative risk is similar to using a Boolean "OR" statement. Only one risk alternative can occur at the same time. For example, if you have a fire risk, the fire could be minor or major each with different outcomes. They are the same risk, but unlike other risk events, these alternatives cannot occur at the same time.

In this example, the risk Fire has two alternatives:

Chance Outcome Result
10% Fixed delay 2 days
2% Relative delay 45%

When the simulations are run, there is a 12% chance that the risk Fire will occur. 10% of the time the outcome of the minor fire will be calculated, while 2% of the time the outcome of a major fire is calculated, but they are never calculated during the same simulation.

What are risk templates and how do they differ from the risk register?

A risk template is a flat list of risks that have been assigned a chance, outcome, result, and distribution. The risk templates can be imported into risk views where you can quickly assign them as global, task, or resource risks. In this way, risk templates provide a quick way of loading risks into your project.

A risk register is a risk management tool that allows you to create, assign, and track risks in greater detail than any of the other risk views. The register allows you to add risk properties, assign ownership, convert risks to issues, and view pre and post mitigation risk scores.

You may share risk register between different computers in your organization by saving it to the corporate server. Using RiskyProject, you may establish simple and easy-to-use corporate risk management system:

  1. Create a risk register and save it on the corporate server (*.alr).
  2. Load the risk register file into a new project.
  3. RiskyProject will ensure that different users do not overwrite the corporate copy of the risk register through the built-in locking mechanism.

How do I use the probabilistic cash flow to as part of my product lifecycle management?

Probabilistic cash flow view is used to present original, actual, and simulation results of cash allocation during monthly, bi-monthly, quarterly and yearly. In RiskyProject, you may apply risks and uncertainties not only to cost, but also to the income. As a result, probabilistic cash flow view will present you with negative cash flow (cost) and positive cash flow (income). It is useful for project lifecycle management, where you are trying to determine both cost associated with product development and income associated with sales of the product.

When should I use probabilistic calendars?

Probabilistic calendars are useful for modeling uncertain scheduling conditions such as weather. If you know from experience that during the project there is a 30% chance that you will be operating under poor weather conditions that will restrict working time, you can create a calendar that reflects this. Using the probabilistic calendars, you can then run this calendar 30% of the time to realistically model weather risks.

How do I customize risk outcomes?

You can add or customize non-schedule risk categories and outcomes (cost and schedule outcomes are hard coded and cannot be edited). RiskyProject provides several default risk categories and outcomes (Legal, Safety, Quality, etc.). You may use Risk Outcomes dialog from Risk menu to add or modify non-schedule risk categories and outcomes. You may also enable or disable certain outcomes, so they are not shown in dropdown list when you do risk assignments.

We recommend that you modify the supplied risk outcomes so that they can be used across your organization. This outcomes are saved in the system registry and can be used for all projects.

I imported schedule from Microsoft Project to RiskyProject. Are any potential differences?

In most cases, if you import your project schedule from Project, the projects in both applications will be identical. However, there are specific cases that may cause slight differences:

  1. RiskyProject currently does not support split tasks. However, RiskyProject will import work calculated using split tasks. RiskyProject does not have task usage or resource usage views. The note for the task will be generated, then the task imported to RiskyProject as a split task.
  2. RiskyProject calculates task duration differently than Microsoft Project in cases where resources that have different calendars are attached to the same task. However, even in these cases, start and finish times of the tasks will be identical.
  3. RiskyProject does not support overtime rates.
  4. RiskyProject does not import resource groups. Each resource is imported individually.
  5. RiskyProject does not support the earned value method “Percent work completed”. Instead, it uses 'Percent completed'.

How can I define opportunities versus threats?


When you create a risk assignment, define a negative outcome result that translates to an opportunity. For example, fixed delay -2 days indicates that if the event occurs, the task will require 2 fewer days to complete and is an opportunity.
How can I import low, base, and high duration from Microsoft Project?
Use the following fields in Microsoft Project to represent Low, Base, and High durations:

Risk assignment

Remember that Duration1 < Duration2 < Duration3

Why is the high result for duration or cost for the current schedule s different from the high results?

Low and high estimates for inputs, which you define for each task, are different from low and high results because their actual meanings are different.

  • You define the definition for low and high estimates for duration, cost, income input in the Distributions tab of Task Information dialog box. This can be interpreted differently depending upon what distributions you select. By default, low distribution inputs are P10 and high is P90.
  • You define the definition of low and high results for duration, cost, and income in the Calculation tab of the Options dialog box as a percentile of statistical distribution obtained as a result of your analysis. By default, low distribution results are P10 and high is P90.
Legal Notice Privacy Statement Copyright © Intaver Institute Inc., 2002-. All Rights Reserved.