RiskyProject for Microsoft Project as a Standalone Application
RiskyProject as a Standalone Application
You can launch RiskyProject directly from the Windows Program menu. When you
open RiskyProject, the main Project view appears in which you can enter schedule
and risk, perform the analysis, track project performance and report the
results.
RiskyProject for Microsoft Project
RiskyProject seamlessly integrates with all versions of Microsoft Project from
2003 and higher. When you install RiskyProject, it checks if Microsoft Project
is installed on the computer. If Microsoft Project 2003/2007 is installed,
RiskyProject and adds a toolbar and macro to Microsoft Project. If Microsoft
Project 2010/2013 is installed RiskyProject installs ribbon tab and Add-In to
Microsoft Project.
Here is how the integration works:
- The first time you open Microsoft Project after installing RiskyProject for Project, check to see that the RiskyProject ribbon tab is visible. You can enable/disable ribbon tab by clicking on Options in the File menu. Project Options dialog will open where you can select Customize Ribbon. You can also check the installed RiskyProject add-in by selecting Add-Ins.
- Create a schedule in Microsoft Project.
- Define uncertainties, perform calculation, and analyze results:
- Define statistical distributions for cost and duration for selected tasks inside Microsoft Project; all statistical distributions are saved in a RiskyProject file.
- Add risk-related information in the RiskyProject views if necessary: risk events, probabilistic and conditional branching, probabilistic calendars, etc.
- Perform Monte Carlo simulations
- View results of analysis and reports in Microsoft Project
- At any moment, you can go back to Microsoft Project and make changes to
your schedule. All changes will be reflected in RiskyProject. However, if you
make changes to the deterministic project schedule in RiskyProject, these
changes may be overwritten by the Microsoft Project schedule.

- You must save the schedule in Microsoft Project to use the integration between
Microsoft Project and RiskyProject.
- Always use the RiskyProject toolbar or ribbon tab in Microsoft Project and
Go back to Microsoft Project button in RiskyProject to move back and forth
between RiskyProject and Microsoft Project.
- Once you have added risks and uncertainties to your schedule in RiskyProject,
they will be always associated with Microsoft Project schedule.
- Once you open
a risk view from within Microsoft Project, your Microsoft Project file will be
associated with the RiskyProject data file that contains risks and uncertainties
for the schedule created in Microsoft Project.
- Links between the Microsoft Project schedule and the RiskyProject file
(alm extension) are saved in the registry. If you move the RiskyProject file
into a different directory, you will be prompted to browse to find the
RiskyProject file associated with Microsoft Project file.
- If you move the Microsoft Project file, the link between Microsoft Project
file and RiskyProject will also be broken. In this case, use the command
File > Import > Risks from Another Project to find the RiskyProject
file.
- If you make any changes in Microsoft Project and open RiskyProject using
the toolbar or ribbon tab, RiskyProject will reflect the change; however, the
risks and uncertainties will be adjusted proportionately. For example, your
schedule in Microsoft Project has a task Project Inception with a Base
duration of 5 days and in RiskyProject you define Low duration as 2 days and
High duration as 6 days. If you go back to Microsoft Project and change the Base
duration to 10 days, when you return to RiskyProject, the Base duration will be
10 days (the same as in Microsoft Project); however, your Low and High durations
will be adjusted proportionately (4 days and 12 days respectively. The same
logic is used if you adjust the original fixed costs, work, income, lag, and
start times.
- Low and high duration and costs are stored in Microsoft Project:
duration1, duration2, duration3 etc. to define low and high duration in
RiskyProject. Statistical distributions are stored in text fields in Microsoft
Projects. You must map the duration, cost, and text fields in Microsoft Project
to low and high duration or cost in RiskyProject using Field Mapping settings.
- Some features of Microsoft Project are not supported in RiskyProject. For
more information, see Frequently Asked Questions.
- You can make changes to the schedule in RiskyProject. However, RiskyProject does
not write these changes, such as task duration or task name, back to the
Microsoft Project schedule. Therefore, we recommend that you do not to make any
changes to original schedule in RiskyProject. Use RiskyProject to add risks,
uncertainties and other risk related information.
- If you want to transfer the original schedule updated in RiskyProject or
results of probabilistic analysis to Microsoft Project, use File >
Launch > Microsoft Project.
|