Search Help:

Managing Uncertainties

If you have accurate historical statistical data that is analogous to a particular element in your project, we recommend that you use this data to model uncertainty in your project as opposed to risk events. Be aware of double-counting risk and uncertainty as most of the uncertainty in a project is due to the probability of risk events occurring.

To define uncertainties:

  1. Define a 3-point estimate for any of task parameters: cost, income, duration, and start time. 3-point estimates for work will be calculated automatically based on uncertainty in duration. You may also define 3-point estimates for the lag.
  2. After you define 3-point estimates, a statistical distribution will be assigned. You may change the default statistical distribution for the duration, cost, income, and start time parameters in Distributions tab of Task Information dialog box.

The meaning of low, base, and high data depends on the statistical distribution defined in the Distributions tab of the Task Information dialog box.


See also

Risks in RiskyProject
Risk Register

Legal Notice Privacy Statement Copyright © Intaver Institute Inc., 2002-. All Rights Reserved.