Search Help:



Changing Risk Visibility

After a risk is created, you may change the list of projects within which the risk is visible.

To change risk visibility:

  1. Click the Risks tab and then in the Risk Views group, click Risk Register or Risky Properties.
  2. Double-click on a Risk ID to open the Risk Information dialog box.
  3. Click the Properties tab.
  4. Select a visibility level. You may choose to make this risk visible:
    • For all projects/all levels of the hierarchy
    • Only at the enterprise level of the hierarchy
    • For specific projects
  5. If you need to make your risk visible for a particular project, click Specific Projects and then the Select Projects button. The Risk Visibility dialog box will open.
  6. Select projects in which you would like your project to be visible.
  7. Click OK.

See also

About Risk Visibility (Approval) Rules

Risk Visibility vs. Risk Assignment